Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : MANGALORE REFINERY AND PETROCHEMICALS LIMITED.
Project Name : DEVANGONTHI MARKETING TERMINAL.

Reported Date : 08-OCT-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 9 / 2024

Cost Overrun (%)-   52

Time Overrun (Months)-    14

Total/Pending/Completed Milestone - 6 / 0 / 6

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
200304304

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
244.1911.680255.87

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20233/20248/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
33.760

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Construction: Substation, Control room, Admin Building, Pump House, Gantry House completed. Pipeline from PMHBL to MRPL Terminal completed. Hydro test also completed and boxed up. Electrical & Instrumentation installations works is in progress. Testing of switchgear panels completed. DCS powered on. Final piping works is in progress, Hydro test of 145 loops completed, Balance in progress. Anticipated Mechanical Completion date is 30.04.2024.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone