| Construction:
Substation, Control room, Admin Building, Pump House, Gantry House completed.
Pipeline from PMHBL to MRPL Terminal completed. Hydro test also completed and boxed up.
Electrical & Instrumentation installations works is in progress. Testing of switchgear panels completed. DCS powered on.
Final piping works is in progress, Hydro test of 145 loops completed, Balance in progress.
Anticipated Mechanical Completion date is 30.04.2024.
|