- Construction:
- Boilers: BOILER 1 &2 are mechanically complete. IBR provisional approval received.
- Reactor:
• Hydrolysis R9202 A - Tank erection and testing completed, Insulation related activities completed.
• Hydrolysis R9202 B – Tank erection completed and hydrotesting completed
• Hydrolysis R9202 C - Tank erection completed and hydrotesting completed
• Hydrolysis R9202 D - Shell and roof erection, welding, and scaffolding completed, insulation ring and spike welding work in progress.
• Pre-fermenter R9304 A – Tank activities completed, punch point issues or liquidation under progress.
• Pre-fermenter R9304 B – Tank activities completed, punch point issues or liquidation under progress.
• Main Fermenter R9305 A - Shell and roof assembly completed, Roof top structure placement and alignment completed.
• Main Fermenter R9305 B - Shell and roof assembly completed, nozzle welding done, hydrotesting completed
• Main Fermenter R9305 C - Tank and roof assembly completed, inside rectification work started and in progress.
- WTP: WTP is mechanically complete, pre commissioning work is in progress.
- ETP: Piping, flooring and E&I work in progress.
- PCTP: All supplies received and mechanical erection completed. E&I works in progress.
- Site Fabricated Tanks: 32 out 2015 MT tank erection balance.
- Equipment erection – 2161 MT of equipment erection completed in the Distillation & Dehydration Unit, Pre-treatments Unit, Evaporation, and various CWI units.
- Electrical and Instrumentation Works – All major electrical panel or equipment are charged/commissioned. Instrument calibration and cable laying in progress. DCS termination ongoing.
- Building works: Completed
- S/L Separation & Boiler Auxiliary Civil Works: Civil Works Completed.
- Reactor Foundation and Milling unit Civil Works: Civil Works Completed.
- Power connection: The main receiving 66kV transformer is energized.
- Commissioning and handing over: NA
| Ordering: As of March 2024, PO placed for 128 tenders out of total 130.
Boilers:DCF-3 Working platform installation work started and under progress
- Reactor:
- Main Fermenter R9305 A: - Bottom Plate placement is completed, Roof Plate, External Structure & Nozzle Fit-up & welding is Completed, Shell pos. No S14, S13, S12, S11, S10, S09, S08 Erection (Placement), welding & grinding is completed, Shell Pos. No. S07 & S06 shell fit up, welding & grinding is under progress. Wind grader Fit-up and welding is completed.
- Main Fermenter R9305 B: - Bottom Plate placement is completed, Roof Plate & External Structure Fit-up & welding is completed, Shell pos. No S14, S13, S12, S11, S10, S09, S08, S07, S06, S05 Erection (Placement), welding & grinding is completed, Wind grader Fit-up and welding is completed, Shell pos. No S04 & S03 Shell welding is under progress, Temporary Structure erection & Jack installation is completed.
- Main Fermenter R9305 C: - Bottom Plate installation & Roof formation completed with Shell pos. 12, 13 & 14 rolling is completed, shell pos. No. S14, S13, S12, S11, S10, S09, S08, S07, S06, S05, S04, S03, S02 Erection, welding & grinding is completed. Wind grader Fit-up and welding is completed. Nozzle Fit up with RF pad is completed. Shell No. 01 Fit-up with Knuckle Plate is under progress.
- Pre-fermenter R9304 A: - Bottom Plate with adjacent shell installation is completed, Nozzle installation with welding on Roof plates is completed and & nozzle fabrication work preparation, Nozzle marking at Roof Plate is complete and all shell pos. No. S01, S02, S03, S04, S05 & S06 welding, grinding & erection on Foundation is completed. Anchor Chair welding is under Progress.
WTP: WTP is mechanically complete |