Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : HINDUSTAN PETROLEUM CORPORATION LIMITED.
Project Name : SECOND GENERATION ETHANOL BIOREFINERY PROJECT, BATHINDA, PUNJAB.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    34

Total/Pending/Completed Milestone - 22 / 3 / 19

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1421.4601421.46

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1135.1418.812.51156.45

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20239/202412/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
244.32244.32

Ministry Review Date

LatestLastPhysical Progress (%)Status
95.62Ongoing

Monthly Status

Background Information

- Construction: - Boilers: BOILER 1 &2 are mechanically complete. IBR provisional approval received. - Reactor: • Hydrolysis R9202 A - Tank erection and testing completed, Insulation related activities completed. • Hydrolysis R9202 B – Tank erection completed and hydrotesting completed • Hydrolysis R9202 C - Tank erection completed and hydrotesting completed • Hydrolysis R9202 D - Shell and roof erection, welding, and scaffolding completed, insulation ring and spike welding work in progress. • Pre-fermenter R9304 A – Tank activities completed, punch point issues or liquidation under progress. • Pre-fermenter R9304 B – Tank activities completed, punch point issues or liquidation under progress. • Main Fermenter R9305 A - Shell and roof assembly completed, Roof top structure placement and alignment completed. • Main Fermenter R9305 B - Shell and roof assembly completed, nozzle welding done, hydrotesting completed • Main Fermenter R9305 C - Tank and roof assembly completed, inside rectification work started and in progress. - WTP: WTP is mechanically complete, pre commissioning work is in progress. - ETP: Piping, flooring and E&I work in progress. - PCTP: All supplies received and mechanical erection completed. E&I works in progress. - Site Fabricated Tanks: 32 out 2015 MT tank erection balance. - Equipment erection – 2161 MT of equipment erection completed in the Distillation & Dehydration Unit, Pre-treatments Unit, Evaporation, and various CWI units. - Electrical and Instrumentation Works – All major electrical panel or equipment are charged/commissioned. Instrument calibration and cable laying in progress. DCS termination ongoing. - Building works: Completed - S/L Separation & Boiler Auxiliary Civil Works: Civil Works Completed. - Reactor Foundation and Milling unit Civil Works: Civil Works Completed. - Power connection: The main receiving 66kV transformer is energized. - Commissioning and handing over: NA Ordering: As of March 2024, PO placed for 128 tenders out of total 130. Boilers:DCF-3 Working platform installation work started and under progress - Reactor: - Main Fermenter R9305 A: - Bottom Plate placement is completed, Roof Plate, External Structure & Nozzle Fit-up & welding is Completed, Shell pos. No S14, S13, S12, S11, S10, S09, S08 Erection (Placement), welding & grinding is completed, Shell Pos. No. S07 & S06 shell fit up, welding & grinding is under progress. Wind grader Fit-up and welding is completed. - Main Fermenter R9305 B: - Bottom Plate placement is completed, Roof Plate & External Structure Fit-up & welding is completed, Shell pos. No S14, S13, S12, S11, S10, S09, S08, S07, S06, S05 Erection (Placement), welding & grinding is completed, Wind grader Fit-up and welding is completed, Shell pos. No S04 & S03 Shell welding is under progress, Temporary Structure erection & Jack installation is completed. - Main Fermenter R9305 C: - Bottom Plate installation & Roof formation completed with Shell pos. 12, 13 & 14 rolling is completed, shell pos. No. S14, S13, S12, S11, S10, S09, S08, S07, S06, S05, S04, S03, S02 Erection, welding & grinding is completed. Wind grader Fit-up and welding is completed. Nozzle Fit up with RF pad is completed. Shell No. 01 Fit-up with Knuckle Plate is under progress. - Pre-fermenter R9304 A: - Bottom Plate with adjacent shell installation is completed, Nozzle installation with welding on Roof plates is completed and & nozzle fabrication work preparation, Nozzle marking at Roof Plate is complete and all shell pos. No. S01, S02, S03, S04, S05 & S06 welding, grinding & erection on Foundation is completed. Anchor Chair welding is under Progress. WTP: WTP is mechanically complete

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone