Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : PETROCHEMICAL AND LUBE INTEGRATION PROJECT AT GUJARAT REFINERY.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 15 / 4 / 11

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
18936018936

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
10530.28341.29290.1711161.74

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
8/202412/202512/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2886.770

Ministry Review Date

LatestLastPhysical Progress (%)Status
82.5Ongoing

Monthly Status

Background Information

60 % model review completed INDMAX. 90% model review completed for ETP Packages, VDU, Boiler Package, DM-ZLD Package, MS Block & Octamax, CDW, PPU, PRU, SRU, Mounded Bullets,Incoming Power Facility, N2-O2 & Compress Air, Cooling Tower and all EPCM units (AU-5, HCU and FCC GDS Revamp, ARU and SWS units). Ordering of all LLI of EPCM and major equipment completed. Piling Job competed. RCC, and Structural jobs under progress. 60 % model review completed INDMAX. 90% model review completed for ETP Packages, VDU, Boiler Package, DM-ZLD Package, MS Block & Octamax, CDW, PPU, PRU, SRU, Mounded Bullets,Incoming Power Facility, N2-O2 & Compress Air, Cooling Tower and all EPCM units (AU-5, HCU and FCC GDS Revamp, ARU and SWS units). Ordering of all LLI of EPCM and major equipment completed. Piling, RCC, and Structural jobs under progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks