60 % model review completed INDMAX.
90% model review completed for ETP Packages, VDU, Boiler Package, DM-ZLD Package, MS Block & Octamax, CDW, PPU, PRU, SRU, Mounded Bullets,Incoming Power Facility, N2-O2 & Compress Air, Cooling Tower and all EPCM units (AU-5, HCU and FCC GDS Revamp, ARU and SWS units).
Ordering of all LLI of EPCM and major equipment completed.
MC achieved for New VDU, Boiler package, RO/DM Plant, Power Import Facility, Cooling Towers, Plant/ Inst Air package, CDW Unit.
RCC, and Structural jobs under progress. | 60 % model review completed INDMAX.
90% model review completed for ETP Packages, VDU, Boiler Package, DM-ZLD Package, MS Block & Octamax, CDW, PPU, PRU, SRU, Mounded Bullets,Incoming Power Facility, N2-O2 & Compress Air, Cooling Tower and all EPCM units (AU-5, HCU and FCC GDS Revamp, ARU and SWS units).
Ordering of all LLI of EPCM and major equipment completed.
Piling, RCC, and Structural jobs under progress. |