Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : PETROCHEMICAL AND LUBE INTEGRATION PROJECT AT GUJARAT REFINERY.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    16

Total/Pending/Completed Milestone - 15 / 4 / 11

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
18936018936

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
10530.2888.58252.7110871.57

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
8/202412/202512/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2886.770

Ministry Review Date

LatestLastPhysical Progress (%)Status
81.9Ongoing

Monthly Status

Background Information

60 % model review completed INDMAX. 90% model review completed for ETP Packages, VDU, Boiler Package, DM-ZLD Package, MS Block & Octamax, CDW, PPU, PRU, SRU, Mounded Bullets,Incoming Power Facility, N2-O2 & Compress Air, Cooling Tower and all EPCM units (AU-5, HCU and FCC GDS Revamp, ARU and SWS units). Ordering of all LLI of EPCM and major equipment completed. MC achieved for New VDU, Boiler package, RO/DM Plant, Power Import Facility, Cooling Towers, Plant/ Inst Air package, CDW Unit. RCC, and Structural jobs under progress. 60 % model review completed INDMAX. 90% model review completed for ETP Packages, VDU, Boiler Package, DM-ZLD Package, MS Block & Octamax, CDW, PPU, PRU, SRU, Mounded Bullets,Incoming Power Facility, N2-O2 & Compress Air, Cooling Tower and all EPCM units (AU-5, HCU and FCC GDS Revamp, ARU and SWS units). Ordering of all LLI of EPCM and major equipment completed. Piling, RCC, and Structural jobs under progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone