Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : AUGUMENTATION OF SALAYA MATHURA CRUDE OIL PIPELINE SYSTEM.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    22

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
161401614

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1081.036.4929.861117.38

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
8/20236/20256/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
66.990

Ministry Review Date

LatestLastPhysical Progress (%)Status
96.21Ongoing

Monthly Status

Background Information

1. Statutory Approvals : Overall Progress (Clearances & Permissions): 100% completed 2. Ordering : Overall Progress of work order(s): 100% completed Overall Progress of purchase order(s): 99.78% completed (including delivery) 3. Manufacturing & Delivery Status : Overall Progress of purchase order(s): 99.78% completed (including delivery) 4. Tendering : Same as details under heading Ordering 5. Construction : Overall Progress: 96.62% completed 6. Commissioning & Hand Over : Overall Progress: 51.26% completed1. Statutory Approvals : Overall Progress: 99.41% completed 2. Ordering : Overall Progress of work order(s): 100% completed Overall Progress of purchase order(s): 99.61% completed (including delivery) 3. Manufacturing & Delivery Status : Overall Progress of purchase order(s): 99.61% completed (including delivery) 4. Construction : Overall Progress: 79.98% completed

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone