Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : CAPACITY EXPANSION OF PANIPAT REFINERY FROM 15 TO 25 MMTPA.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 23 / 0 / 23

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
346273823138231

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
19053.361825.6575.9421454.9

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/202412/202512/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
7087.540

Ministry Review Date

LatestLastPhysical Progress (%)Status
87.6Ongoing

Monthly Status

Background Information

90% model review completed for all units except RHCU unit. LLI Ordering completed and manufacturing & delivery is in progress. RCC, structural fabrication, erection and Piping fabrication and erection jobs are in progress.90% model review completed for all units except RHCU unit. LLI Ordering completed and manufacturing & delivery is in progress. RCC, structural fabrication, erection and Piping fabrication and erection jobs are in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks