Reported Date :
05-MAY-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
4
/
2025
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
12
|
Total/Pending/Completed Milestone -
62
/
0
/
62
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
| •Land development and Approach road works: Completed.
•Compound wall works: 60% completed. Termination of M/s. Aakriti done on 05.09.2023 due to poor performance.
•Compound wall (balance proposed TT parking workings): 23% completed. Total - 1690/ 3610 m of compound wall are completed with plastering.
•Civil Building Works: 52% works are completed.
•Structure Shed and allied jobs: 89% work has been completed.
•ETP works: Civil works 98 % of the work has been completed.
•Dyke Wall: 70% work completed.
•TT Gantry Misc Shed: 38% Civil Jobs completed.
•Roads Drain: 34% work are completed.
•RCC Driveway works: 30% work are completed.
•Formation Works-Railway Siding: Work completed, punch points are under compliance.
•Permanent Way Works : 82% of the work has been completed
•OHE works: 22% work are completed.
•Signal telecommunication work : SECR, Raipur Division has placed the LOI on Vendor 22.02.2024. Excavation and laying of cable are in progress.
•Construction of Fire Water Tanks : TK 401 TK 402 -Mechanically completed including hydrotesting with RCC apron and painting.
•Product tanks- HSD tanks: TK 201 and TK 202-Mechanically completed including hydrotesting with RCC apron. MS Tanks: TK 105 and TK 106-Mechanically completed- including hydrotesting .
•Fire Water piping product piping jobs : 55% work completed.
•UG Tanks: 55% work completed..
•Cased Crossing Jobs (FCI Track): Cased crossing supply items like Casing insulators, Insulation Joints fittings received. Preparatory works for installation of Boring Machine completed.
•Electrical Works: 15% physical progress achieved.
•CCTV Works: 70% Physical Progress achieved.
•Automation works: 66% work are completed. |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |