Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : CGD PROJECT AT BOKARO, HAZARIBAGH AND RAMGARH DISTRICTS.

Reported Date : 24-MAY-24

Monthly Report : 5 / 2024

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
6130613

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
226.15.470226.62

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20293/20303/2030

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
27.220

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Extension received from PNGRB due to COVID - 19 & non - availability of pipeline connectivity in the vicinity of the GA.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks