Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : CGD PROJECT AT REWA DISTRICT.

Reported Date : 24-MAY-24

Monthly Report : 5 / 2024

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1770177

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
109.48.280109.76

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20279/20289/2028

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
19.380

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Extension received from PNGRB due to COVID - 19. No Time overrun, Original Completion date is extended by PNGRB.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks