Reported Date :
24-MAY-24
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
5
/
2024
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
3
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
| Extension received from PNGRB due to Flood, COVID - 19 & non - availability of pipeline connectivity in
the vicinity of the GA."
|
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |