Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : CGD PROJECT AT MUZAFFARPUR, VAISHALI, SARAN AND SAMASTIPUR DISTRICTS.

Reported Date : 24-MAY-24

Monthly Report : 5 / 2024

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
299602996

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
568.643.660572.3

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20288/20298/2029

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
41.830

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Extension received from PNGRB due to Flood & COVID - 19. No Time overrun, Original Completion date is extended by PNGRB.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks