Store room building- plastering work in progress.
¿ Roads: 75% work in progress.
¿ ETP Control Room work in progress- 100% brick work completed.
¿ GGS Electrical Subtation- 50% Plaster work Completed.
¿ Elevated Pipe Support -100% of RCC completed.
Fire Water Pump Shed, NSF Transfer Pump Shed, Clarifier Storage Sump, Booster cum Backwash pump shed
work in progress.
¿
¿ Pipe Rack- Fabrication in progress.
Crude Oil Storage Tanks (4nos), Wash Tank, Raw Water tank, Treated Water Storage Tanks, Treated Water
Feed Tank fit-up and erection in progress.
¿
¿ Piping Work - 70% completed.
Erection of following items completed: Seperators, Gas scrubber, LP HP Compressor packages, Effluent
Disposal Pumps to Effluent Injection Manifold | Facilities:
• NOA placed to M/s HAL Offshore on 29.09.2023 after additional sanction was obtained by Mehsana Asset.
¿ TPI Agency: NoA to M/s Rina India Pvt. Ltd placed on 19.12.2023
¿ Approval of insurance policies completed.
¿ Area Mark-up in prgress for administrative building, Parking shed, Tanks etc.
¿ 2 Land parcels of appx. area 11,000 m2 are yet to be acquired. Acquistion in progress thru SPLO route.
¿ Planning package approved
¿ Plot plan submitted and observation conveyed to LSTK.
¿ Contract signed with TPI agency on 16/01/2024.
¿ New Land filling contract awarded to M/s Gayatri Construction on 09/02/2024.
Drilling of wells:
• Total drilling of 32/38 wells completed. |