Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL & NATURAL GAS CORPORATION LIMITED.
Project Name : REDEVELOPMENT OF LINCH FIELD.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   36.29

Time Overrun (Months)-    4

Total/Pending/Completed Milestone - 3 / 2 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
631.03860.04860.04

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
384.82.314.54399.66

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20250/07/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1100

Ministry Review Date

LatestLastPhysical Progress (%)Status
31-MAY-2575.8Ongoing

Monthly Status

Background Information

Store room building- plastering work in progress. ¿ Roads: 75% work in progress. ¿ ETP Control Room work in progress- 100% brick work completed. ¿ GGS Electrical Subtation- 50% Plaster work Completed. ¿ Elevated Pipe Support -100% of RCC completed. Fire Water Pump Shed, NSF Transfer Pump Shed, Clarifier Storage Sump, Booster cum Backwash pump shed work in progress. ¿ ¿ Pipe Rack- Fabrication in progress. Crude Oil Storage Tanks (4nos), Wash Tank, Raw Water tank, Treated Water Storage Tanks, Treated Water Feed Tank fit-up and erection in progress. ¿ ¿ Piping Work - 70% completed. Erection of following items completed: Seperators, Gas scrubber, LP HP Compressor packages, Effluent Disposal Pumps to Effluent Injection ManifoldFacilities: • NOA placed to M/s HAL Offshore on 29.09.2023 after additional sanction was obtained by Mehsana Asset. ¿ TPI Agency: NoA to M/s Rina India Pvt. Ltd placed on 19.12.2023 ¿ Approval of insurance policies completed. ¿ Area Mark-up in prgress for administrative building, Parking shed, Tanks etc. ¿ 2 Land parcels of appx. area 11,000 m2 are yet to be acquired. Acquistion in progress thru SPLO route. ¿ Planning package approved ¿ Plot plan submitted and observation conveyed to LSTK. ¿ Contract signed with TPI agency on 16/01/2024. ¿ New Land filling contract awarded to M/s Gayatri Construction on 09/02/2024. Drilling of wells: • Total drilling of 32/38 wells completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone