Drilling of 38/38 wells completed.(32 OP+4ED + 2 WI)Facility Status: The project demonstrates strong progress across all key areas with engineering at 94.50% completion (target 100%), procurement at 94.59%, and construction at 77.42%. Engineering has achieved significant milestones with 467 of 545 documents approved by DEC/ONGC, completion of HAZOP study and 90% model review at Petro6 Chennai, and two interim delay analysis reports signed. Procurement is well-advanced with all 86 purchase orders placed (36 long-lead and 50 non-long-lead items) and major equipment delivered including GDU packages, gas compressors, transformers, and processing units from vendors like Indcon, Siemens, and Veolia. Construction activities are progressing with admin building finishing work underway and GGS control room building plaster work completed. The project maintains steady momentum toward completion despite some schedule variance in construction activities. | Facilities:
• NOA placed to M/s HAL Offshore on 29.09.2023 after additional sanction was obtained by Mehsana Asset.
¿ TPI Agency: NoA to M/s Rina India Pvt. Ltd placed on 19.12.2023
¿ Approval of insurance policies completed.
¿ Area Mark-up in prgress for administrative building, Parking shed, Tanks etc.
¿ 2 Land parcels of appx. area 11,000 m2 are yet to be acquired. Acquistion in progress thru SPLO route.
¿ Planning package approved
¿ Plot plan submitted and observation conveyed to LSTK.
¿ Contract signed with TPI agency on 16/01/2024.
¿ New Land filling contract awarded to M/s Gayatri Construction on 09/02/2024.
Drilling of wells:
• Total drilling of 32/38 wells completed. |