Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : GAS AUTHORITY OF INDIA LIMITED.
Project Name : 60 KTA POLYPROPYLENE PROJECT.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 17 / 2 / 15

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
910.561299.021299.02

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
950.410.613974

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20244/20247/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
105199

Ministry Review Date

LatestLastPhysical Progress (%)Status
96.9Ongoing

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks