GGS-I: - Admin Building: Completed. Finishing contd. Substation Building: plaster work and panel erection contd.
Control room Building: Completed. Cabling and Fall ceiling work completed. - Bath Heater, Sheds, Manifold,
Instrument air compressor foundations, pump shed and well flow line support completed. Erection of Test,
Activation and group seperator , Gas scrubber, BH, Instrument Air compressor, Diesel unloading pump done.
Boundary wall , Group Separator & flare foundation, Culvert, Road, test and activation pump foundation work
contd. Manifold and Well flow line support completed.
¿
GGS-II: - Admin build: Completed, Electrical work contd. Control room building: completed. Cabling work contd.
Substation Building: plaster work and panel & transformer erection contd. Wash tank with dyke wall, foundations,
sheds, manifold foundation. Erection of all gas Lift Compressor, 3 Pre-heater, Heater treater, Bath Heater &
separator , FGC, Flare done. - GDu erection, well flow lines, Road & Culvert work, flare footing contd. Boundary
wall completed. | Facilities:
• NOA for Design & Engineering Consultant (DEC) placed to M/s Oriental EPC Pvt Ltd on 06.12.2021.
• NIT for LSTK contract held on 28.07.2022. Pre Bid conference held on 18.08.2022
• Meeting with DEC held on 30th and 31st August’2022 for costing and pre-bid replies.
• Land acquisition for GGS-II and CTF Sobhasan are in progress.
• NIT Issued on 28.07.2022. NOA placed to M/s HAL Offshore on 29.09.2023 after additional sanction was obtained by Mehsana Asset. Planning package approved.
* Boundry wall construction at CTF, GGS-I and GGS-II is in progress.
* New Land filling contract awarded to M/s Gayatri Construction on 09/02/2024.
* PO placed for Compressor (4 units)
Drilling of wells:
• Drilling of 50/75 wells completed. |