Basic Engineering Completed. Detail Engineering in progress.
POs placed for EPCM Contract, Soil Investigation, Air Blower, Slide Valves, Exchangers, PSVs, Barrel Pump and Centrifugal pumps, vessels, Reciprocating Pumps, Civil Works, Agitator, desuperheater & PMCC Extension panel, Pipes , fittings, flanges, valves gaskets & bolts for MTO I, RR Package and Mechanical Execution
works, ON OFF valves, Temperature element, Ultrasonic flow element, Lift, DFAH and refractory.
Execution - Statutory Approvals received. 19/26 tie-ins are completed. Underground survey completed. Soil investigation completed. Area Clearance completed. Excavation works completed and combined raft (840 cu.m)
concreting completed. Structural material – 326/350 MT material received at site. Air Blower Foundation completed and balance equipment’s and pedestal for technological structure in progress. Structural erection for RR Package in progress.
Testing and inspection of 4 slide valves completed. Vessels, Pipes and Fittings received at site. Air blower dispatched from vendor works, Fabrication of RR package in
progress. | EPCM (Engineering, Procurement and Construction Management) contract finalized on M/s. PDIL. POs placed for Main Air Blower (MAB), Soil investigation and Slide Valves. Cum.23/50 PRs released. PQC Completed for Civil Contract. Tender released for RR Package. 66% Detail engineering completed. Site Clearance completed |