Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL & NATURAL GAS CORPORATION LIMITED.
Project Name : GAS ASSISTED GRAVITY DRAINAGE SCHEME, KASOMARIGAON.

Reported Date : 07-JAN-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 12 / 2024

Cost Overrun (%)-   0

Time Overrun (Months)-    21

Total/Pending/Completed Milestone - 5 / 0 / 5

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
218.380218.38

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
79.01138.990218

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20236/202411/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
102.060

Ministry Review Date

LatestLastPhysical Progress (%)Status
31-DEC-24100Completed

Monthly Status

Background Information

Project completed on 01.11. 2024.Facilities: • NOA for surface facilities placed on M/s Sopan O&M Co. Pvt. Ltd. Pune on 13.08.2021. • Pre- engineering Site survey carried out. Geo technical, topography, Contour survey and soil resistivity test Inside boundary completed. Design, Engineering and Procurment in progress. Planning package approved. • Purchase Orders placed for 88 major items. • Fixing of boundary pillars by forest Officials and fencing on acquired land done on 07.11.2022. • Consent to establish obtained on 21.12.22. Site was handed over on 24.12.2022. Soil survey completed on additional land. Three Phase Power connection for construction activities at site completed. Inspection of pre-cast boundary wall completed. * Compressor package received at site on 27.04.2023. Fabrication works of crude storage tanks is in progress. Boundary wall Construction, crude storage tank foundation, Road construction, are under progress. HP, LP & Test Separator, KOD foundation work completed. Piling work for crude storage tank and compressor foundation completed. * Fabrication works of crude storage tanks is in progress. * Construction of boundary wall is 100% completed. Erection of Gas Compressor package, HP, LP and Test Separator has been completed. Civil work for control room building, road and pipe sleepers is in progress. Drilling of wells: • 1 out of 4 wells completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone