Project completed on 01.11.
2024. | Facilities:
• NOA for surface facilities placed on M/s Sopan O&M Co. Pvt. Ltd. Pune on 13.08.2021.
• Pre- engineering Site survey carried out. Geo technical, topography, Contour survey and soil resistivity test Inside boundary completed. Design, Engineering and Procurment in progress. Planning package approved.
• Purchase Orders placed for 88 major items.
• Fixing of boundary pillars by forest Officials and fencing on acquired land done on 07.11.2022.
• Consent to establish obtained on 21.12.22. Site was handed over on 24.12.2022. Soil survey completed on additional land. Three Phase Power connection for construction activities at site completed. Inspection of pre-cast boundary wall completed.
* Compressor package received at site on 27.04.2023. Fabrication works of crude storage tanks is in progress. Boundary wall Construction, crude storage tank
foundation, Road construction, are under progress. HP, LP & Test Separator, KOD foundation work completed. Piling work for crude storage tank and compressor foundation completed.
* Fabrication works of crude storage tanks is in progress.
* Construction of boundary wall is 100% completed. Erection of Gas Compressor package, HP, LP and Test Separator has been completed. Civil work for control room building, road and
pipe sleepers is in progress.
Drilling of wells:
• 1 out of 4 wells completed. |