Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : NEW MUNDRA-PANIPAT CRUDE OIL PIPELINE.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    14

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
902809028

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
4925.51408.47209.636543.6

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/202412/202512/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2108.510

Ministry Review Date

LatestLastPhysical Progress (%)Status
77.53Ongoing

Monthly Status

Background Information

l Statutory Approvals : Overall Progress (Clearances & Permissions): 100% completed 2 Ordering : Overall Progress for work order(s): 100% completed Overall Progress for purchase order(s): 99.49% completed 3 Manufacturing & Delivery Status : Overall Progress: 95.75% completed 4 Construction : Overall Progress: 58.17% completed 1. Statutory Approvals : Overall Progress: 99.61% completed Working permission of Wildlife clearance from Churwa to IPS-1 (Bhabhar) received on 21.03.2024. 2. Ordering : Overall Progress for work order(s): 96.37% completed Overall Progress for purchase order(s): 97.58% completed 3. Manufacturing & Delivery Status : Overall Progress: 77.81% completed 4. Construction : Overall Progress: 19.66% completed Total 648 km RoU opening, 501 km welding & 253 Km lowering completed. Foundation stone laid by Honble PM on 25.02.2024.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone