l Statutory Approvals :
Overall Progress (Clearances & Permissions): 100% completed
2 Ordering :
Overall Progress for work order(s): 100% completed
Overall Progress for purchase order(s): 99.49% completed
3 Manufacturing & Delivery Status :
Overall Progress: 95.75% completed
4 Construction :
Overall Progress: 58.17% completed
| 1. Statutory Approvals :
Overall Progress: 99.61% completed
Working permission of Wildlife clearance from Churwa to IPS-1 (Bhabhar) received on 21.03.2024.
2. Ordering :
Overall Progress for work order(s): 96.37% completed
Overall Progress for purchase order(s): 97.58% completed
3. Manufacturing & Delivery Status :
Overall Progress: 77.81% completed
4. Construction :
Overall Progress: 19.66% completed
Total 648 km RoU opening, 501 km welding & 253 Km lowering completed.
Foundation stone laid by Honble PM on 25.02.2024. |