Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : NEW MUNDRA-PANIPAT CRUDE OIL PIPELINE.

Reported Date : 13-MAR-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 4 / 2024

Cost Overrun (%)-   0

Time Overrun (Months)-    2

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
902809028

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
4925.5072.824998.32

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/202412/202412/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2108.510

Ministry Review Date

LatestLastPhysical Progress (%)Status
58.09Ongoing

Monthly Status

Background Information

1. Statutory Approvals : Overall Progress: 99.74% completed 2. Ordering : Overall Progress for work order(s): 96.37% completed Overall Progress for purchase order(s): 98.05% completed 3. Manufacturing & Delivery Status : Overall Progress: 80.03% completed 4. Construction : Overall Progress: 23.09% completed Total 734 km RoU opening, 580 km welding & 320 Km lowering completed. Foundation stone laid by Honble PM on 25.02.2024.Mundra Tank farm works: foundation for 7 out of 9 Nos. tanks in progress. l Switchyard works: Manufacturing of GIS in progress. l CSW works: Installation of job pile for boundary wall in progress. 16/558 job piles installed IPS-1 (Bhabhar): Switchyard works: Mobilization in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone