1. Statutory Approvals :
Overall Progress: 99.74% completed
2. Ordering :
Overall Progress for work order(s): 96.37% completed
Overall Progress for purchase order(s): 98.05% completed
3. Manufacturing & Delivery Status :
Overall Progress: 80.03% completed
4. Construction :
Overall Progress: 23.09% completed
Total 734 km RoU opening, 580 km welding & 320 Km lowering completed.
Foundation stone laid by Honble PM on 25.02.2024. | Mundra
Tank farm works: foundation for 7 out of 9 Nos. tanks in progress.
l Switchyard works: Manufacturing of GIS in progress.
l CSW works: Installation of job pile for boundary wall in progress. 16/558 job piles installed
IPS-1 (Bhabhar):
Switchyard works: Mobilization in progress. |