Project completed on 31.03.2025. | • NOA placed on M/s L&T Hydrocarbon Engineering Limited on 24.01.2022. Contract signed on 09.03.2022 with M/s LTHE.
• Planning Package submitted by L&T was approved by competent authority on 02.06.2022.
• Design, Engineering and procurement in progress.
• Pre Engineering Pipeline Route survey completed and Survey for Topside modification is in progress.
• All Line pipes ordering completed, manufacturing of Line pipes are in progress. Coating work in progress. Fabrication of Riser clamp, Piping spool, Piles (Free span correction), Structural is in progress at Hazira Yard.
* Barge ENA Habitat (Topside modification), Barge Seamec Princess (Crossing & Free span correction), OSV Triton Harmony & OSV Greatship Vimla (Assisting in Topside modification) are still in field. Total 168.90 Km of Pipeline laid (14 Segments) before demobilization of Vessel (40.62 Km Pipe lay of PRP-VI- balance Change
order work and 128.28 Km of PRPVII Scope).
* Pipeline laying of total 14 segments completed. 10 pipeline segments handed over to Assets
* Top-side modification work in progress.
* Balance subsea works of PRP-VI is in progress. |