1) Civil Works (Non-Plant Buildings):- WIP (54%)
• Construction works in progress for Admin building, MCC building, Control Room, TT Crew Room, Canteen Building, Storeroom, Security Room-A&B, Workshop, Culverts, roads, drains, TTPA, main gate erection and road pavement in main entrance.
2) Mechanical works (Tankage-1):- WIP (86%)
• Hydrotest completed for all 3nos. Box up completed.
• Erection works in progress for 1 product tanks. 3 nos. product tank mechanically completed and hydrotest completed
• Dyke wall and impervious flooring works in progress
3) Mechanical works (Plant building/ Pipeline):- WIP (53%)
• • Erection works completed for Fire water Pump house.
• Erection works of TLF shed in progress.
• Foundation/ Structural works for Product pump house/pipe bridge/ cable bridge in progress.
• Product / Hydrant Pipeline – Pedestals & pipe fabrication/laying - WIP
4) Electrical works: - WIP (59%)
• Brought out Materials ordered and delivery of materials nearing completion. HMT foundation / erection works (7/8 completed) and light fitting works, earthing strip works, cable laying, trench, fabrication and LT panel base frame works completed, panel installation to commence and DG positioning in PMCC room completed.
5) Automation works: - WIP (46%)
• LOA placed on 27.04.2024. Brought out Materials ordered and delivery of materials in progress. FAT for automation system completed.
6) Mechanical Works (Tankage 2 – ATF/BD/UG):-
• LOA placed on 27.05.2024. Contractual Formalities completed and site to be handed over as and when work fonts are available.
7) Vapour Recovery Unit: WIP (43%)
• LOA placed on 01.02.2024. Detailed design/document approval in progress. Order placed for brought out items. CAPEX order placed for carrying out VRU foundation works. | Land development & boundary wall - WIP(99.75%)
Mechanical-1(Tankage) - WIP(59%)
Pipeline and Plant Building - WIP(27.00%)
Civil Package (Non Plant Building) - WIP (28.00%)
Electrical Package - WIP (23.00%) |