Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : GRASS ROOT POL TERMINAL AT VALLUR, CHENNAI.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
827887.71887.71

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
560.6915.944.31580.94

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20246/202512/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1350

Ministry Review Date

LatestLastPhysical Progress (%)Status
85.9Ongoing

Monthly Status

Background Information

Land development works completed. WIP for Tankage Fabrication & Dyke wall works (76.5%), non plant building (83%), Mechanical-2 Package for Pipeline (83%), Electrical works(85%), Automation (78.5%), VRU (70%) and Civil-3 for Road & Drain (43%).Site handed over and land development works completed (100%). WIP for Tankage Fabrication & Dyke wall works (52%), non plant building (43%), Mechanical-2 Package for Pipeline (44%), Electrical works(35%), Automation (35%), VRU (5%) and Civil-3 for Road & Drain (5%).

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks