Reported Date :
15-APR-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
5
/
2025
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
36
|
Total/Pending/Completed Milestone -
18
/
5
/
13
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
| i)Physical Progress: 80.40% Financial Progress: 57.77%, the actual expenditure till date is Rs 5352.74 Crore and commitment is Rs 7914 Crore.
ii)Construction activities of all three phases are in progress. Total welding of about 967 Km and 847 Km total pipeline laying completed till date. |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |