Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDRADHANUSH GAS GRID LTD.
Project Name : NORTH EAST GAS GRID.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    36

Total/Pending/Completed Milestone - 18 / 5 / 13

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
926592659265

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
6270.19006270.19

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20247/20253/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1000611.92

Ministry Review Date

LatestLastPhysical Progress (%)Status
24-MAR-2584.51Ongoing

Monthly Status

Background Information

i)Physical Progress: 80.40% Financial Progress: 57.77%, the actual expenditure till date is Rs 5352.74 Crore and commitment is Rs 7914 Crore. ii)Construction activities of all three phases are in progress. Total welding of about 967 Km and 847 Km total pipeline laying completed till date.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone