Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : HINDUSTAN PETROLEUM CORPORATION LIMITED.
Project Name : BHATINDA SANGRUR PIPELINE.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   8.17

Time Overrun (Months)-    14

Total/Pending/Completed Milestone - 43 / 3 / 40

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
367397397

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
315.5214.07.22329.81

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
5/20242/20257/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2828

Ministry Review Date

LatestLastPhysical Progress (%)Status
06-FEB-2590.3Ongoing

Monthly Status

Background Information

"""Statutory Approvals Prior Approval of PESO for pipeline received on August 23, 2022. CTE for pipeline received on September 19, 2022. Prior Approval of PESO for Bathinda depot received on November 17, 2022. CTE for Bathinda depot received on December 10, 2022. 3(1) Gazette notification published for entire Bathinda-Sangrur Pipeline on 07.02.2022. 6(1) Gazette notification published for entire Bathinda-Sangrur Pipeline on 10.10.2022 Final permission obtained for 275 out of 275 crossings Engineering Basic Engineering Completed on March 17, 2022. Detailed engineering Completed on March 30, 2023. Land Acquisition Registration of land for SV-02 completed on 07.11.2022. Registration of land for SV-01 completed on 16.11.2022. Manufacturing All major materials are manufactured and delivered at site. Ordering Order Placement completed for 48 out of 48 packages. Tendering Tendering completed for 48 out of 48 packages. Construction Panchanama for pipeline laying under progress. Welding completed for 83.2 km and Lowering for 83.1 km. Civil works completed for SV-1,SV-2 Control Building and MCC Building at Bathinda station. Composite Works completed at Bathinda Dispatch Station and Sangrur Receiving Station. Electrical Panels testing and commissioning completed in all locations.PLC panels installation and IO testing completed at all locations. OISD Pre-commissioning Safety Audit completed and completion approval obtained on 22.07.2024. Product Received in Sangrur Terminal Tanks on 24th September 2024.”” """Statutory Approvals Prior Approval of PESO for pipeline received on August 23, 2022. CTE for pipeline received on September 19, 2022. Prior Approval of PESO for Bathinda depot received on November 17, 2022. CTE for Bathinda depot received on December 10, 2022. 3(1) Gazette notification published for entire Bathinda-Sangrur Pipeline on 07.02.2022. 6(1) Gazette notification published for entire Bathinda-Sangrur Pipeline on 10.10.2022 Final permission obtained for 275 out of 275 crossings Engineering Basic Engineering Completed on March 17, 2022. Detailed engineering Completed on March 30, 2023. Land Acquisition Registration of land for SV-02 completed on 07.11.2022. Registration of land for SV-01 completed on 16.11.2022. Manufacturing Delivery of line pipes,OFC,Scrapper barrels,Density skid,PCV, MFM,PIDS,DPCV, MBV,BF,45KVA UPS, Mainline Pumps,Underground Valves and MV Panels completed. Manufacturing in progress for Valves,UPS,HV Panels and Field instruments. Delivery of steel plates,ETP equipment,FW pumps,Loading arms,Transformer, Pipeline fittings,DG set,Product pumps,DBBV,Ball valves,Gate valves,electrical cables,MV Panels,Jockey and Foam Pumps,Pipes and SRV completed. Ordering Order Placement completed for 48 out of 48 packages. Tendering Tendering completed for 48 out of 48 packages. Construction Panchanama for pipeline laying under progress. Welding completed for 37.8 km and Lowering for 30.9 km. Slab Casting, Brick work, Plastering and RCC Trenches completed for SV-1,SV-2 Control Building and MCC Building at Bathinda station. Placing of Hume pipes for ERC/IRC completed. PEB Fabrication works and erection completed. Erection of Pig barrels,Basket filter,MFM, Pumps,VFD Panels and 45 KVA AC UPS completed. Tank foundation and Fabrication works completed.Hydrotesting of 8 out of 8 tanks completed in Sangrur. Construction completed for MCC room,Control room, Drivers and Sample room. Structure erection for TT gantry,Foam shed,Calibration shed, FWPH and PPH completed. Erection of Transformer,DG sets,LED lights,Density skid completed.Piping works completed. Electrical works and TAS in progress at Sangrur.""”

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone