"""Statutory Approvals
Prior Approval of PESO for pipeline received on August 23, 2022. CTE for pipeline received on September 19, 2022.
Prior Approval of PESO for Bathinda depot received on November 17, 2022. CTE for Bathinda depot received on December 10, 2022.
3(1) Gazette notification published for entire Bathinda-Sangrur Pipeline on 07.02.2022.
6(1) Gazette notification published for entire Bathinda-Sangrur Pipeline on 10.10.2022
Final permission obtained for 275 out of 275 crossings
Engineering
Basic Engineering Completed on March 17, 2022. Detailed engineering Completed on March 30, 2023.
Land Acquisition
Registration of land for SV-02 completed on 07.11.2022.
Registration of land for SV-01 completed on 16.11.2022.
Manufacturing
All major materials are manufactured and delivered at site.
Ordering
Order Placement completed for 48 out of 48 packages.
Tendering
Tendering completed for 48 out of 48 packages.
Construction
Panchanama for pipeline laying under progress. Welding completed for 83.2 km and Lowering for 83.1 km.
Civil works completed for SV-1,SV-2 Control Building and MCC Building at Bathinda station. Composite Works completed at Bathinda Dispatch Station and Sangrur Receiving Station. Electrical Panels testing and commissioning completed in all locations.PLC panels installation and IO testing completed at all locations.
OISD Pre-commissioning Safety Audit completed and completion approval obtained on 22.07.2024. Product Received in Sangrur Terminal Tanks on 24th September 2024.””
| """Statutory Approvals
Prior Approval of PESO for pipeline received on August 23, 2022. CTE for pipeline received on September 19, 2022.
Prior Approval of PESO for Bathinda depot received on November 17, 2022. CTE for Bathinda depot received on December 10, 2022.
3(1) Gazette notification published for entire Bathinda-Sangrur Pipeline on 07.02.2022.
6(1) Gazette notification published for entire Bathinda-Sangrur Pipeline on 10.10.2022
Final permission obtained for 275 out of 275 crossings
Engineering
Basic Engineering Completed on March 17, 2022. Detailed engineering Completed on March 30, 2023.
Land Acquisition
Registration of land for SV-02 completed on 07.11.2022.
Registration of land for SV-01 completed on 16.11.2022.
Manufacturing
Delivery of line pipes,OFC,Scrapper barrels,Density skid,PCV, MFM,PIDS,DPCV, MBV,BF,45KVA UPS, Mainline Pumps,Underground Valves and MV Panels completed. Manufacturing in progress for Valves,UPS,HV Panels and Field instruments.
Delivery of steel plates,ETP equipment,FW pumps,Loading arms,Transformer, Pipeline fittings,DG set,Product pumps,DBBV,Ball valves,Gate valves,electrical cables,MV Panels,Jockey and Foam Pumps,Pipes and SRV completed.
Ordering
Order Placement completed for 48 out of 48 packages.
Tendering
Tendering completed for 48 out of 48 packages.
Construction
Panchanama for pipeline laying under progress. Welding completed for 37.8 km and Lowering for 30.9 km.
Slab Casting, Brick work, Plastering and RCC Trenches completed for SV-1,SV-2 Control Building and MCC Building at Bathinda station. Placing of Hume pipes for ERC/IRC completed. PEB Fabrication works and erection completed. Erection of Pig barrels,Basket filter,MFM, Pumps,VFD Panels and 45 KVA AC UPS completed.
Tank foundation and Fabrication works completed.Hydrotesting of 8 out of 8 tanks completed in Sangrur. Construction completed for MCC room,Control room, Drivers and Sample room.
Structure erection for TT gantry,Foam shed,Calibration shed, FWPH and PPH completed. Erection of Transformer,DG sets,LED lights,Density skid completed.Piping works completed. Electrical works and TAS in progress at Sangrur.""”
|