Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : REVAMPING OF FACILITIES AT EXISTING GUWAHATI TERMINAL, ASSAM.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    2

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2770277

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
175.6904.48180.17

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20269/20269/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
500

Ministry Review Date

LatestLastPhysical Progress (%)Status
66.4Ongoing

Monthly Status

Background Information

1) Civil Works • Package-I (Land Dev., Invoice Room, Driver’s Rest Room, FW Pump House, Checking Platform & Internal B/wall): Completed • Package-II (Non-Plant Buildings, Roads, Drains): WIP (94.50%) o Works of Peripheral Road around TTPA, Approach Road Entry/ Exit, Internal Roads/Drains completed o Construction of Store cum OCH Bldg (G+1), Security Room and new PMCC Building completed. o Control Room: Mezzanine Floor Slab casted, Superstructure work in progress. • Package-III (Approach Roads, Drains, TTPA & Driveway/pavement): WIP (58.50%) o Work of Approach Road & Drain completed o TTPA Development work in progress. o Segregation wall, Drains work in progress 2) Mechanical works • Package-I (2Nos Fire Water Tanks, 1 MS Tank & 1 HSD Tank): Completed. • Package-II (Piping, TLF, Plant Building): WIP (88.50%) o Fire Pumps trial run completed successfully & Commissioned. o Product Pump House completed, manifold in progress. o Tank Farm manifold completed Work in progress for OWS Pipeline, Fire Hydrant Line, and cable bridge erection. 3) Electrical works: WIP (65.00%) o Design & Engineering completed. Procurement: Orders placed, being delivered progressively. Fire Water Panel delivered & commissioned. o High Masts with fixtures, Cable Trays, Cables, DG Set, Transformers, PCC Panel delivered. Installation work in progress. 4) VRU: WIP (57.50%) o Design & Engineering completed. o Equipment Procurement in process. Shop fabrication in progress. Mechanical Package-I (Tanks): Work in Progress-97%. Civil-I package (Land Development& Dyke): Work in progress-99.90%. Mechanical Package-II (Pipelines / Plant Bldgs): Work in progress-40.70%. Civil-II package (Plant Building): Work in progress-46.10%

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone