Tendering and ordering completed, Site construction works in progress. Mechanical works in progress for DWST tanks. ISBL and OSBL pipeline works in progress. Pipeline works in progress at JNPT jetty
|
1)ISBL Piling works : Casting of 2060/ 2197 piles completed. Piling completed for both DWST tanks, Compressor shed, Fire water tank, ERV shed, control room, substation and staircase.New work order placed on 20.09.2023 for completing balance piling works of ISBL. Works of the same commenced at site, 89 out of 270 Pile casted
2)OSBL Civil and Piling works: Casting of 549/760 WSEL( Wedge Shear Elelment Layer) foundation completed. Nine test piles completed including Vertical and Lateral Load test for piles with 21M depth. Total 1893 out of 1893 working pile casted. Steel support erection for new 20" pipeline under progress Total 206.8 / 226 MT steel support erection completed.
|