Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : BHARAT PETROLEUM CORPORATION LIMITED.
Project Name : DEBOTTLENECKING AND AUGMENTATION OF CRYOGENIC FACILITIES AT URAN LPG IMPORT TERMINAL.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    10

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1164.6901164.69

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
791.2336.5845.22873.03

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20240/04/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2500

Ministry Review Date

LatestLastPhysical Progress (%)Status
82.2Ongoing

Monthly Status

Background Information

Tendering and ordering completed, Site construction works in progress. Mechanical works in progress for DWST tanks. ISBL and OSBL pipeline works in progress. Pipeline works in progress at JNPT jetty 1)ISBL Piling works : Casting of 2060/ 2197 piles completed. Piling completed for both DWST tanks, Compressor shed, Fire water tank, ERV shed, control room, substation and staircase.New work order placed on 20.09.2023 for completing balance piling works of ISBL. Works of the same commenced at site, 89 out of 270 Pile casted 2)OSBL Civil and Piling works: Casting of 549/760 WSEL( Wedge Shear Elelment Layer) foundation completed. Nine test piles completed including Vertical and Lateral Load test for piles with 21M depth. Total 1893 out of 1893 working pile casted. Steel support erection for new 20" pipeline under progress Total 206.8 / 226 MT steel support erection completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone