Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL & NATURAL GAS CORPORATION LIMITED.
Project Name : CREATION OF GAS DEHYDRATION FACILITIES.

Reported Date : 13-MAR-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 4 / 2024

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 2 / 1 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
209.330131.51

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
12.810.0412.85

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
5/20240/05/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
300

Ministry Review Date

LatestLastPhysical Progress (%)Status
30-APR-2438.8Ongoing

Monthly Status

Background Information

• NOA placed for facilities on M/s Multitex Filtration Engineering Ltd. New Delhi on 31.03.2022. Kick off meeting of the contract held on 25.04.2022. • Pre-engineering survey completed. Planning package approved. • Hazard identification study (HAZID) completed on 11.10.2022 and Hazardous Operability (HAZOP) study on 14.10.2022. • Design, engineering, procurement and manufacturing are in progress. Procurement and Manufacturing Status: * All 21 nos Glycol Circulation Pumps arrived at site. Shutdown Valves for Konaban Arrived at site 8 no of standalone equipment (2 no Inlet separator, 2 no Overhead scrubber and 4 no particulate filters) reached to Konaban site on 08.04.2023 01 no Fuel Gas KOD, 02 nos Glycol Flash Drum, 04 nos Charcoal Filters, 02 nos Surge Drum received at Konsaban site. 04 nos Particulate Filters, 02 nos Fuel Gas KOD and 02 nos Flash Drum received at site Total 37 vessels (Konaban-27, Sonamura-5, Gojalia-5) arrived at site out of 67. * LOI/PO placed for Energy Exchange Pump, Antifoam and Ph Corrosion Inhibitor Skid, Shut down valves, Column internals & dual chamber orifice meter, restricted orifice meter, manual valves, control valves and restriction orifice. 01 no Fuel Gas KOD, 02 nos Glycol Flash Drum, 04 nos Charcoal Filters, 02 nos Surge Drum dispatched for Konaban site. Total 37 vessels arrived at site out of 67 Construction Progress : * KONABAN SITE Total no of major foundations = 10 no (Rev), RCC foundations completed for = 07 no RCC foundations in progress = 3 no * GOJALIA SITE Total no of major foundations = 6 no (Rev) RCC foundations completed for = 02 no RCC foundations in progress = 02 no * SONAMURA SITE 5 no standalone equipment PCC works completed. Reinforcement cutting works for all major foundation works are in progress. Total no of major foundations = 06 no(Rev), RCC foundations completed for = 0 no RCC foundations in progress = 03 no

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone

   <