Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL & NATURAL GAS CORPORATION LIMITED.
Project Name : COMMERCIAL POLYMER FLOODING PROJECT IN BECHRAJI FIELD.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    12

Total/Pending/Completed Milestone - 2 / 1 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
621.40621.4

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
130.27.490137.69

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/20240/011/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
75.960

Ministry Review Date

LatestLastPhysical Progress (%)Status
31-MAY-2521.4Ongoing

Monthly Status

Background Information

Board agenda for revised sanction considering hired polymer injection facility is being put up. ¿ After Board approval, NIT for creation of surface facilities will be published. ¿ Way forward for the facilities is under process. ¿ Drilling of 27/63 wells completed. 27 wells (10 PI + 17 OP) Facility: • NOA for Design and Engineering Consultant (DEC) placed on 12.04.2022 to M/s PDIL Baroda. • DEC made site visit to Technical bid preparation. Meeting held with DEC, Asset and OES on 17th & 18th August-22 for scope finalization. • Tender is being prepared by consultant in three groups. Final TBP for Group B submitted by DEC on 10.02.2023. Bid package submitted to Asset for approval. Costing evaluation in progress. Execution methodology approved. * Milestone Payement Formula, Purhase Specification & Special Contract condition approved. * De-Scope is required (due to revised costs wrt FR)and is in process. Drilling: • Drilling of 22/63 wells completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone