Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL & NATURAL GAS CORPORATION LIMITED.
Project Name : COMMERCIAL POLYMER FLOODING PROJECT IN BECHRAJI FIELD.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 2 / 1 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
621.40621.4

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
130.27.490137.69

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/20240/011/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
75.960

Ministry Review Date

LatestLastPhysical Progress (%)Status
30-JUN-2521.4Ongoing

Monthly Status

Background Information

The Design and Engineering Consultant (DEC) project awarded to M/s PDIL Baroda in April 2022 has completed technical bid preparation and received approvals for key execution parameters. Due to cost escalations, the project strategy has been revised to hire polymer injection facilities instead of owning them, enabling early oil realization at reduced costs. De-scoping has been implemented to align with revised financial parameters. The project is currently awaiting board approval for the revised sanction incorporating the hired facility model, after which NIT for surface facilities will be published. Drilling operations show strong progress with 27 of 63 wells completed (10 PI + 17 OP wells), while the way forward for facilities is under finalization.RetryClaude can make mistakes. Please double-check responses.Facility: • NOA for Design and Engineering Consultant (DEC) placed on 12.04.2022 to M/s PDIL Baroda. • DEC made site visit to Technical bid preparation. Meeting held with DEC, Asset and OES on 17th & 18th August-22 for scope finalization. • Tender is being prepared by consultant in three groups. Final TBP for Group B submitted by DEC on 10.02.2023. Bid package submitted to Asset for approval. Costing evaluation in progress. Execution methodology approved. * Milestone Payement Formula, Purhase Specification & Special Contract condition approved. * De-Scope is required (due to revised costs wrt FR)and is in process. Drilling: • Drilling of 22/63 wells completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

   <