Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL & NATURAL GAS CORPORATION LIMITED.
Project Name : DEVELOPMENT OF JHARIA CBM BLOCK (PHASE-1).

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    17

Total/Pending/Completed Milestone - 3 / 2 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
4310431

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
132.8340.3911.46184.68

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
1/20243/20256/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
12.1252.94

Ministry Review Date

LatestLastPhysical Progress (%)Status
31-MAR-2557.8Ongoing

Monthly Status

Background Information

Foundation for Gas Metering skid, DEG & GEG completed. Other foundation work in progress Facility Progress (Plan: 100 % Actual: 72.93 %): Design & Engineering_GCS - Plan: 100% Actual: 97.94%, Procurement_GCS- Plan: 100.0% Actual: 98.24%,?? Construction_GCS- Plan: 100% Actual: 91.73%, Hook up_GCS- Plan: 100% Actual: 0%, Commissioning_GCS- Plan: 100% Actual: 0%, Design & Engineering_Pipeline- Plan: 100% Actual: 9.1%, Procurement_pipeline- Plan: 100% Actual: 99.85%, Pipe Line Laying- Plan: 100% Actual: 62.14 %, Hook up_Pipeline- Plan: 100% Actual: 0%, Commissioning_Pipeline- Plan: 100% Actual: 0% Drilling of 11/36 wells completed.Facilities: • Contract for facilities awarded to M/s Equinox Engineering Limited on 22.03.2022 and Kick-Off Meeting (KOM) held on 28.04.2022 at Bokaro Asset. * DCI & MCI has been approved. * Pre engineering survey report submitted on 29.08.2022 • LOI placed for DEG, CS line pipes, Flare stack and metering skid, separators (feed gas and water separator), control system, Jockey Pump, Level transmitter etc. Transformers received at site. • M/s Lakshya Powertech approved as sub-contractor for Construction, installation & commissioning activities. • Site Civil activities started from 27.01.2023. Topography survey for 8 manifolds completed. Revalidation of route survey for pipeline route alignment completed. Other civil works in progress. * Electrical substation: Excavation & PCC completed. Rebar Cutting, Bending in Progress * Topograhy Survey and Soil testing for 8 manifolds completed. * Inspection of Plate for GDU fabrication done on 29.07.23. * Pipeline punchnama in progress by ONGC. Upto date approx. 9.26km/61 km ROU punchnama completed * Foundation for Gas Metering skid, DEG & GEG completed. Other foundation work in progress Drilling: * Drilling of 11/36 wells completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone

   <