Electrical substation: Excavation & PCC completed. Rebar Cutting, Bending in Progress
Inspection completed and Likely to be dispatched: Process Gas Compressors 02 Nos. received at site. ,Fuel Gas
Compressors
Under Inspection and likely to be dispatched: GDU, Second Gas Filter, Diesel storage Tank ,Jockey pumps etc.
Construction Site Activities: Foundation of all equipments and sheds completed. Parking shed, Watch Towers,
High Mast Tower, Sheds for Produced water pumps, Fire water Pumps etc completed.
Work under progress for Admin Building, Control Building, Electrical Substation, Security Accomodation, Roads,
Boundary walls etc under progress.
Pipeline Work: ROU Punchnama by ONGC. Upto date approx. 9.259 km/40 km ROU total Pipeline Length 79.00
Km. C.S Pipline: Stringing 5405.640, Welding 3804.00 & Lowering 1852.00 HDPE Pipeline: Stringing 4764.00,
Welding 3612 & Lowering 1440. GCS Piping: Total Scope 26916.33 ID, Fabrication(Fit-UP) done of 15283.00 ID,
Fabrication(Welding) done of 14459 ID, Piping Erection done 1122 IM out of 47881 IM.~11 kms/ 79 kms pipeline
laid across PWD road/ONGC road
Foundation for Gas Metering skid, DEG & GEG completed. Other foundation work in progress. | Facilities:
• Contract for facilities awarded to M/s Equinox Engineering Limited on 22.03.2022 and Kick-Off Meeting (KOM) held on 28.04.2022 at Bokaro Asset.
* DCI & MCI has been approved.
* Pre engineering survey report submitted on 29.08.2022
• LOI placed for DEG, CS line pipes, Flare stack and metering skid, separators (feed gas and water separator), control system, Jockey Pump, Level transmitter etc. Transformers received at site.
• M/s Lakshya Powertech approved as sub-contractor for Construction, installation & commissioning activities.
• Site Civil activities started from 27.01.2023. Topography survey for 8 manifolds completed. Revalidation of route survey for pipeline route alignment completed. Other civil works in progress.
* Electrical substation: Excavation & PCC completed. Rebar Cutting, Bending in Progress
* Topograhy Survey and Soil testing for 8 manifolds completed.
* Inspection of Plate for GDU fabrication done on 29.07.23.
* Pipeline punchnama in progress by ONGC. Upto date approx. 9.26km/61 km ROU punchnama completed
* Foundation for Gas Metering skid, DEG & GEG completed. Other foundation work in progress
Drilling:
* Drilling of 11/36 wells completed. |