| Facilities:
• Contract for facilities awarded to M/s Equinox Engineering Limited on 22.03.2022 and Kick-Off Meeting (KOM) held on 28.04.2022 at Bokaro Asset.
* DCI & MCI has been approved.
* Pre engineering survey report submitted on 29.08.2022
• LOI placed for DEG, CS line pipes, Flare stack and metering skid, separators (feed gas and water separator), control system, Jockey Pump, Level transmitter etc. Transformers received at site.
• M/s Lakshya Powertech approved as sub-contractor for Construction, installation & commissioning activities.
• Site Civil activities started from 27.01.2023. Topography survey for 8 manifolds completed. Revalidation of route survey for pipeline route alignment completed. Other civil works in progress.
* Electrical substation: Excavation & PCC completed. Rebar Cutting, Bending in Progress
* Topograhy Survey and Soil testing for 8 manifolds completed.
* Inspection of Plate for GDU fabrication done on 29.07.23.
* Pipeline punchnama in progress by ONGC. Upto date approx. 9.26km/61 km ROU punchnama completed
* Foundation for Gas Metering skid, DEG & GEG completed. Other foundation work in progress
Drilling:
* Drilling of 11/36 wells completed. |