Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : EXPANSION OF CRYOGENICS GROUP BY SETTING UP NEW MANUFACTURING FACILITY.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    20

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
3780378

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
120.07022.24142.31

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20236/20256/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
123123

Ministry Review Date

LatestLastPhysical Progress (%)Status
90.6Ongoing

Monthly Status

Background Information

Substation Building completed. Boundary wall completed. Erection of all PEB sheds completed. All entry Gates completed. Utility building completed for all PEB sheds . Finishing works such as painting are in progress . Road & drain Work are in progress. Admin Building architectural work is in progress. Electrical Cables of Approx. 73 km sited. HT and LT panels, Earthing strip, main transformer 3150 kva installed and other earthing materials sited. Work in progress for cable tray GI strip cable laying wiring earthing pit etc. Normal 40 KVA and Emergency 150KVA transformer sited .DG of 500 KVA and 250 KVA installed . Bus duct sited. Installation of street light poles are in progress. Sprinkler and Fire Hydrant work Eighty Five Percentage work completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone