Reported Date :
15-APR-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
5
/
2025
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
20
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Substation Building completed.
Boundary wall completed.
Erection of all PEB sheds completed.
All entry Gates completed.
Utility building completed for all PEB sheds .
Finishing works such as painting are in progress .
Road & drain Work are in progress.
Admin Building architectural work is in progress.
Electrical Cables of Approx. 73 km sited. HT and LT panels, Earthing strip, main transformer 3150 kva installed and other earthing materials sited. Work in progress for cable tray GI strip cable laying wiring earthing pit etc. Normal 40 KVA and Emergency 150KVA transformer sited .DG of 500 KVA and 250 KVA installed . Bus duct sited. Installation of street light poles are in progress.
Sprinkler and Fire Hydrant work Eighty Five Percentage work completed.
| |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |