Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : HINDUSTAN PETROLEUM CORPORATION LIMITED.
Project Name : NEW LPG PLANT AT VARANASI.

Reported Date : 27-MAR-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   10.15

Time Overrun (Months)-    -3

Total/Pending/Completed Milestone - 19 / 0 / 19

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
194.62214.37214.37

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
132.7455.270188.01

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
5/20245/20242/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
5858

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone