Activities completed/ongoing in the month of May 2025: Piping jobs in pipe rack 4 by Mechanical packager in progress: 91% completed. Pipe support jobs are in progress – 85% completed. GDU package foundation jobs in new location in progress. Erection of GDU package in progress. Electrical Heater to heater control panel cable laying jobs in progress. Piping jobs in EPS area in progress.
Project Progress details: Package-1 : Sch. 100 % / Act. 100%.FGGS Baghjan Package-2A : Sch. 90.50%/ Act. 68.77%.FGGS Baghjan Package-2B : Sch. 93.10%/ Act. 84.50%.FGGS Baghjan Package-2C : Sch. 94.10% / Act. 92.27 %.FGGS Baghjan Package-2D : Sch. 94.10%/ Act. 93.83%.FGGS Baghjan Package-3 : Sch. 90.90% / Act.83.60%.FGGS Baghjan Package-4 : Sch. 93.80%/ Act. 88.82%.FGGS Baghjan Package-5 : Sch. 88.14%/ Act. 72.10%.FGGS Baghjan Package-6 : Sch. 85.39%/ Act.75.21% | The Project EDC has been revised as 31.12.2024 & accordingly schedule has been reworked.• Manufacturing of GDU procurement items are in progress. Partial dispatch in progress.
• Pipe fabrication jobs and erection jobs in progress.
• Substation fabrication work in advanced completion phase.
• Operators Accommodation internal in progress.
• Pipe rack: Erection jobs in segment 3 in progress. Foundation for pipe rack 3, 4 & 5 completed.
|