9. Activities completed/ongoing in the month of June 2025
• Piping jobs in pipe rack 4 by Mechanical packager in progress: 95% completed.
• Pipe support jobs are in progress – 86% completed.
• Erection of GDU package in progress in old area and new area.
• Electrical Heater to heater control panel cable laying jobs in progress.
• Piping jobs in EPS area in progress.
• Completion of Flare KOD construction
Presently Incessant rain slowing down the pace of the project -¿ Use of mud mats, de-watering pumps, diverting the accumulated water through constructed drains. | The Project EDC has been revised as 31.12.2024 & accordingly schedule has been reworked.• Manufacturing of GDU procurement items are in progress. Partial dispatch in progress.
• Pipe fabrication jobs and erection jobs in progress.
• Substation fabrication work in advanced completion phase.
• Operators Accommodation internal in progress.
• Pipe rack: Erection jobs in segment 3 in progress. Foundation for pipe rack 3, 4 & 5 completed.
|