Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL INDIA LIMITED.
Project Name : PROJECT TO CONSTRUCT A FIELD GAS GATHERING STATION AT BAGHJAN AREA FOR COLLECTION,PROCESSING.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    11

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
430.760430.76

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
307.71.210.96319.86

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20243/20246/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
123.060

Ministry Review Date

LatestLastPhysical Progress (%)Status
31-MAY-2583.66Ongoing

Monthly Status

Background Information

Activities completed/ongoing in the month of May 2025: Piping jobs in pipe rack 4 by Mechanical packager in progress: 91% completed. Pipe support jobs are in progress – 85% completed. GDU package foundation jobs in new location in progress. Erection of GDU package in progress. Electrical Heater to heater control panel cable laying jobs in progress. Piping jobs in EPS area in progress. Project Progress details: Package-1 : Sch. 100 % / Act. 100%.FGGS Baghjan Package-2A : Sch. 90.50%/ Act. 68.77%.FGGS Baghjan Package-2B : Sch. 93.10%/ Act. 84.50%.FGGS Baghjan Package-2C : Sch. 94.10% / Act. 92.27 %.FGGS Baghjan Package-2D : Sch. 94.10%/ Act. 93.83%.FGGS Baghjan Package-3 : Sch. 90.90% / Act.83.60%.FGGS Baghjan Package-4 : Sch. 93.80%/ Act. 88.82%.FGGS Baghjan Package-5 : Sch. 88.14%/ Act. 72.10%.FGGS Baghjan Package-6 : Sch. 85.39%/ Act.75.21%The Project EDC has been revised as 31.12.2024 & accordingly schedule has been reworked.• Manufacturing of GDU procurement items are in progress. Partial dispatch in progress. • Pipe fabrication jobs and erection jobs in progress. • Substation fabrication work in advanced completion phase. • Operators Accommodation internal in progress. • Pipe rack: Erection jobs in segment 3 in progress. Foundation for pipe rack 3, 4 & 5 completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone