Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : BHARAT PETROLEUM CORPORATION LIMITED.
Project Name : CONSTRUCTION OF LUBE OIL BLENDING AND FILLING PLANT AT RASAYANI.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    6

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
423.390423.39

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
233.218.4511.47253.13

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20240/09/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1600

Ministry Review Date

LatestLastPhysical Progress (%)Status
75.5Ongoing

Monthly Status

Background Information

Majority of packages awarded, Site construction works in progress. 75.53% physical progress achieved. 1)Construction of boundary wall completed. 2) 6/6 High mast installed. 3) Fire water tank:Completed . 4) Tank Lorry Gantry : Civil & structural works completed, sheeting works in progress 5)Product Tanks: Tank foundation work completed for 70/70 Tanks. 63 tanks erected. 6)Amenities Building : Completed and finishing works in progress. 7)FWPH :Civil works completed. Finishing works in progress 8) Planning cum control room Completed and finishing works in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone