Reported Date :
15-APR-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
5
/
2025
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
6
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Majority of packages awarded, Site construction works in progress. 75.53% physical progress achieved.
| 1)Construction of boundary wall completed.
2) 6/6 High mast installed.
3) Fire water tank:Completed .
4) Tank Lorry Gantry : Civil & structural works completed, sheeting works in progress
5)Product Tanks: Tank foundation work completed for 70/70 Tanks. 63 tanks erected.
6)Amenities Building : Completed and finishing works in progress.
7)FWPH :Civil works completed. Finishing works in progress
8) Planning cum control room Completed and finishing works in progress.
|
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |