Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : INSTALLATION OF BITUMEN MANUFACTURING UNIT ALONG WITH ALLIED FACILITIES AT BARAUNI.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
3890389

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
32.64.011.6438.25

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20250/05/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
148.840

Ministry Review Date

LatestLastPhysical Progress (%)Status
35.4Ongoing

Monthly Status

Background Information

Tender floated for all LLIs (Long Lead Item). PO issued for all LLI Enabling & Geo technical Survey: Job completed. Tankage Tender awarded. KOM dome Construction: Piling job in progress Tender floated for all LLIs (Long Lead Item). Reactor : PO issued on 16.01.24. Rotary Pump : PO Issued on 29.03.24. Incinerator Package including Scrubber : Under PBO approval Geo technical Survey: Job in progress. Tankage Tender floated on 22.03.24. Enabling job (M/s BRKS): Dismantling job in progress. All jobs completed except acid tank removal.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks