Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : INSTALLATION OF BITUMEN MANUFACTURING UNIT ALONG WITH ALLIED FACILITIES AT BARAUNI.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    13

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
3890389

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
32.64.95-.9436.61

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20250/05/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
148.840

Ministry Review Date

LatestLastPhysical Progress (%)Status
33.7Ongoing

Monthly Status

Background Information

Tender floated for all LLIs (Long Lead Item). PO issued for all LLI Enabling & Geo technical Survey: Job completed. Tankage Tender awarded. KOM dome Construction: Piling job in progressTender floated for all LLIs (Long Lead Item). Reactor : PO issued on 16.01.24. Rotary Pump : PO Issued on 29.03.24. Incinerator Package including Scrubber : Under PBO approval Geo technical Survey: Job in progress. Tankage Tender floated on 22.03.24. Enabling job (M/s BRKS): Dismantling job in progress. All jobs completed except acid tank removal.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone