Reported Date :
15-APR-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
5
/
2025
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
20
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Topography job awarded to M/s Gaveshana Geoscience on 28.12.22 and soil investigation works awarded to Bhaskaram Jyotish Anushandhan Kendra on 03.01.23.
Reactors and tankages job awarded.
Final CTE received on 09.11.2023
Erection & and Welding of all 10 Nos Shell completed for Tank T-001A and T-011B. Nozzles welding in progress.
BBU Unit: Incineratore area 54 nos. piling out of 67 nos. completed.
Civil/Structural & UG Piping work in progress for BBU and Offsite area.
| Topography job awarded to M/s Gaveshana Geoscience on 28.12.22 and soil investigation works awarded to Bhaskaram Jyotish Anushandhan Kendra on 03.01.23.
Reactors and tankages job awarded.
Final CTE received on 09.11.2023
|
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |