1. Statutory Approvals :
Overall Progress: 100% completed
2. Ordering :
Overall Progress of work order(s): 100% completed
Overall Progress of purchase order(s): 100% completed
3. Manufacturing & Delivery Status :
Overall Progress: 86.12% completed
4. Construction :
Overall Progress: 20.14% completed | A. Manufacturing & Delivery Status :
Overall Progress: 64.9% completed
B. Construction:
Overall Progress: 10.16% completed
1. Mainline works: Work commenced on 18.08.2023. 16.81 km welding and 9.92 km lowering completed out of 49.79 km as on 08.02.2024
2. Foundation stone laid on 02.01.2024 by Honble Prime Minister.
3. On 08.02.2024, Honorable High Court of Delhi passed an order restraining IOCL from proceeding further with the laying of Common Corridor Pipelines for grass root terminal at Vallur during the pendency of the writ petition filed
by M/s IMC seeking stay on subject pipelines. In view of this, the project activities are on hold. |