Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : LAYING OF POL PIPELINES IN COMMON CORRIDOR FOR PROPOSED GRASS ROOT TERMINAL AT VALLUR (CHENNAI).

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
8290829

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
237.3720.171.94259.48

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20245/20265/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
263.370

Ministry Review Date

LatestLastPhysical Progress (%)Status
60.16Ongoing

Monthly Status

Background Information

1. Statutory Approvals : Overall Progress: 100% completed 2. Ordering : Overall Progress of work order(s): 100% completed Overall Progress of purchase order(s): 100% completed 3. Manufacturing & Delivery Status : Overall Progress: 86.13% completed 4. Construction : Overall Progress: 21.96% completed Foundation stone laid on 02.01.2024 by Honorable Prime Minister. On 08.02.2024, Honorable High Court of Delhi passed an order restraining IOCL from proceeding further with the laying of Common Corridor Pipelines for grass root terminal at Vallur during the pendency of the writ petition filed by M/s IMC seeking stay on subject pipelines. The same got vacated on 14.08.2024A. Manufacturing & Delivery Status : Overall Progress: 64.9% completed B. Construction: Overall Progress: 10.16% completed 1. Mainline works: Work commenced on 18.08.2023. 16.81 km welding and 9.92 km lowering completed out of 49.79 km as on 08.02.2024 2. Foundation stone laid on 02.01.2024 by Honble Prime Minister. 3. On 08.02.2024, Honorable High Court of Delhi passed an order restraining IOCL from proceeding further with the laying of Common Corridor Pipelines for grass root terminal at Vallur during the pendency of the writ petition filed by M/s IMC seeking stay on subject pipelines. In view of this, the project activities are on hold.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks