Reported Date :
15-APR-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
5
/
2025
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
7
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
1. Statutory Approvals :
Overall Progress (Clearances & Permissions): 99.65% completed
2. Ordering :
Overall Progress of work order(s): 100% completed
Overall Progress of purchase order(s): 100% completed
3. Manufacturing & Delivery Status :
Overall Progress: 93.78% completed
4. Engineering :
100% Completed
5. Construction :
Overall Progress: 32.20% completed | 1. Statutory Approvals :
Overall Progress: 61.40% completed
2. Ordering :
Overall Progress of work order(s): 100% completed
Overall Progress of purchase order(s): 76.02% completed
3. Manufacturing & Delivery Status :
Overall Progress: 57.59% completed |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |