Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : ATF PIPELINE FROM JAWAHARLAL NEHRU PORT TRUST (JNPT) TO NAVI MUMBAI INTERNATIONAL AIRPORT (NMIA).

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    7

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1650165

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
72.192.663.7578.6

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
8/20250/03/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
35.980

Ministry Review Date

LatestLastPhysical Progress (%)Status
65.93Ongoing

Monthly Status

Background Information

1. Statutory Approvals : Overall Progress (Clearances & Permissions): 99.65% completed 2. Ordering : Overall Progress of work order(s): 100% completed Overall Progress of purchase order(s): 100% completed 3. Manufacturing & Delivery Status : Overall Progress: 93.78% completed 4. Engineering : 100% Completed 5. Construction : Overall Progress: 32.20% completed1. Statutory Approvals : Overall Progress: 61.40% completed 2. Ordering : Overall Progress of work order(s): 100% completed Overall Progress of purchase order(s): 76.02% completed 3. Manufacturing & Delivery Status : Overall Progress: 57.59% completed

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone