Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : CAPACITY EXPANSION OF DIGBOI REFINERY FROM 0.65 TO 1.0 MMTPA.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    5

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
7680768

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
80.15.196.4186.75

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20250/03/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
144.550

Ministry Review Date

LatestLastPhysical Progress (%)Status
33.1Ongoing

Monthly Status

Background Information

Detailed engineering is in progress. HAZOP completed. Soil investigation, topographical survey and UG scanning works completed. Piling job is in progress. All 4 LLI ordered. (Pre cracker reactor, Naphtha Stabiliser Column and Flasher Column). AVU Furnace modification package: Awarded to M/s Thermax on 18.10.2024. Civil Structural & UG Piping works (Part A): Awarded to M/s NEECON on 28.02.2025. Building Works: Awarded to M/s Navrup on 06.03.2025. Stone Column Piling works for tankages: Awarded to M/s Keller on 07.02.2025. DCU Heater Secondary Furnace: Awarded to M/s BHEL. Mechanical work for Tankages work: PBO is under approval. Cooling tower tender: Awarded to M/s Paharpur. Soil investigation, topographical survey and UG scanning works completed. Site grading and preparation activities are in progress Tank dismantling and demolition works completed. 501 / 800 Nos. of Piling job completed. Detailed engineering is in progress. HAZOP completed. Enabling works in progress. Tenders floated for DCU Furnace Heater Package, 3/4 LLI ordered. Pre cracker reactor, Naphtha Stabiliser Column and Flasher Column.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone