Detailed engineering is in progress. HAZOP completed.
Soil investigation, topographical survey and UG scanning works completed. Piling job is in progress.
All 4 LLI ordered. (Pre cracker reactor, Naphtha Stabiliser Column and Flasher Column).
AVU Furnace modification package: Awarded to M/s Thermax on 18.10.2024.
Civil Structural & UG Piping works (Part A): Awarded to M/s NEECON on 28.02.2025.
Building Works: Awarded to M/s Navrup on 06.03.2025.
Stone Column Piling works for tankages: Awarded to M/s Keller on 07.02.2025.
DCU Heater Secondary Furnace: Awarded to M/s BHEL.
Mechanical work for Tankages work: PBO is under approval.
Cooling tower tender: Awarded to M/s Paharpur.
Soil investigation, topographical survey and UG scanning works completed.
Site grading and preparation activities are in progress
Tank dismantling and demolition works completed.
501 / 800 Nos. of Piling job completed.
| Detailed engineering is in progress. HAZOP completed.
Enabling works in progress.
Tenders floated for DCU Furnace Heater Package, 3/4 LLI ordered. Pre cracker reactor, Naphtha Stabiliser Column and Flasher Column. |