Reported Date :
15-APR-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
5
/
2025
|
Cost Overrun (%)- 102.1
|
Time Overrun (Months)-
15
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Engineering
90% Model review (Ph-1) completed.
Tendering
LSTK for ISBL Jobs: awarded to M/s tkIS on 28.04.2023.
OSBL Civil & Structural tender: Awarded to M/s Hariom Builders 25.07.23. KOM on 28.12.23.
Cooling tower tender awarded to M/s Hamon.
Ordering
All (12/12) LLI & Critical Items ordered.
Construction
All civil & structural agencies mobilized at site (3 LSTK + 2 EPCM).
Piling Job completed. OSBL common pipe rack (PBR+MAH) job in progress at site. | Engineering
60% Model review (Ph-1) completed on 09.02.24. OSBL: 30% Model review completed on 05.12.23.
Tendering
LSTK for ISBL Jobs: awarded to M/s tkIS on 28.04.2023.
OSBL Civil & Structural tender: Awarded to M/s Hariom Builders 25.07.23. KOM on 28.12.23.
Cooling tower tender floated on 09.01.2024. Under TQ/CQ.
Ordering
All (12/12) LLI & Critical Items ordered.
Construction
All civil & structural agencies mobilized at site. Site enabling jobs are in progress. |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |