Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : POLY BUTADIENE RUBBER PLANT AT PANIPAT.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   102.1

Time Overrun (Months)-    15

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
14592948.622948.62

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
875.4828.969.48913.92

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20256/20266/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
393.710

Ministry Review Date

LatestLastPhysical Progress (%)Status
65.6Ongoing

Monthly Status

Background Information

Engineering 90% Model review (Ph-1) completed. Tendering LSTK for ISBL Jobs: awarded to M/s tkIS on 28.04.2023. OSBL Civil & Structural tender: Awarded to M/s Hariom Builders 25.07.23. KOM on 28.12.23. Cooling tower tender awarded to M/s Hamon. Ordering All (12/12) LLI & Critical Items ordered. Construction All civil & structural agencies mobilized at site (3 LSTK + 2 EPCM). Piling Job completed. OSBL common pipe rack (PBR+MAH) job in progress at site.Engineering 60% Model review (Ph-1) completed on 09.02.24. OSBL: 30% Model review completed on 05.12.23. Tendering LSTK for ISBL Jobs: awarded to M/s tkIS on 28.04.2023. OSBL Civil & Structural tender: Awarded to M/s Hariom Builders 25.07.23. KOM on 28.12.23. Cooling tower tender floated on 09.01.2024. Under TQ/CQ. Ordering All (12/12) LLI & Critical Items ordered. Construction All civil & structural agencies mobilized at site. Site enabling jobs are in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone