Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : BHARAT PETROLEUM CORPORATION LIMITED.
Project Name : CITY GAS DISTRIBUTION NETWORK PROJECT AT AHMEDNAGAR AND AURANGABAD.

Reported Date : 08-APR-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 14 / 2 / 12

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
3972.1803972.18

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1079.83378.5958.581517

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20280/09/2028

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
3500

Ministry Review Date

LatestLastPhysical Progress (%)Status
46.1Completed

Monthly Status

Background Information

1)Steel Pipeline: 5280 inch-km of steel pipeline lowering achieved. 2)PNG-D connections: Total 97408 nos. PNG-D connections have been established. 3)CNG Stations: Construction of 114 CNG Stations completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone