Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : BHARAT PETROLEUM CORPORATION LIMITED.
Project Name : CITY GAS DISTRIBUTION NETWORK PROJECT AT SANGLI AND SATARA.

Reported Date : 08-APR-24

Monthly Report : 3 / 2024

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2337.9802337.98

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
553.45186.5814.98755.01

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/20280/011/2028

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2800

Ministry Review Date

LatestLastPhysical Progress (%)Status
49.1Completed

Monthly Status

Background Information

Till March 2024, (1) Total 2847 inkm of steel pipeline is laid (2) Total 69864 nos. PNG-D connections have been established.(3) Construction of 76 CNG Station completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks