Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : BHARAT PETROLEUM CORPORATION LIMITED.
Project Name : CITY GAS DISTRIBUTION NETWORK PROJECT AT BALLARI AND GADAG.

Reported Date : 08-APR-24

Monthly Report : 3 / 2024

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
897.620897.62

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
167.4636.526.82210.8

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20280/09/2028

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
650

Ministry Review Date

LatestLastPhysical Progress (%)Status
49.6Completed

Monthly Status

Background Information

• A total of 869 inch-km of steel pipeline is laid • A total of 14376 nos. PNG-D connections have been established. • 35 CNG Station have been Commissioned

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks