Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : BHARAT PETROLEUM CORPORATION LIMITED.
Project Name : CITY GAS DISTRIBUTION NETWORK PROJECT AT BARGARH, DEBGARH AND SAMBALPUR.

Reported Date : 08-APR-24

Monthly Report : 3 / 2024

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
599.190599.19

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
143.8780.249233.11

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20300/03/2030

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
400

Ministry Review Date

LatestLastPhysical Progress (%)Status
62.4Completed

Monthly Status

Background Information

Till March 2024, (1 Total 793 inch km of steel pipeline is laid (2) 5542 nos. PNG-D connections infrastructure have been established. (3) 25 CNG station mechanically completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks