Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : BHARAT PETROLEUM CORPORATION LIMITED.
Project Name : CITY GAS DISTRIBUTION NETWORK PROJECT AT BILASPUR, HAMIRPUR AND UNA.

Reported Date : 08-APR-24

Monthly Report : 3 / 2024

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
427.940427.94

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
58.2620.891.0180.16

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20300/09/2030

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
200

Ministry Review Date

LatestLastPhysical Progress (%)Status
50.1Completed

Monthly Status

Background Information

• Total 7715 nos. PNG-D connections have been established. • 11 CNG stations commissioned. • 8 CNG stations are in operation.