Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : BHARAT PETROLEUM CORPORATION LIMITED.
Project Name : CITY GAS DISTRIBUTION NETWORK PROJECT AT SIDHI AND SANGRAULI.

Reported Date : 08-APR-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
350.350350.35

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
63.5715.986.1985.74

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20290/03/2029

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
400

Ministry Review Date

LatestLastPhysical Progress (%)Status
39.7Completed

Monthly Status

Background Information

Till March 24, (1) Total 196 inkm of steel pipeline is laid (2) Total 3538 nos. PNG-D connections have been established. (3) Total 11 nos CNG station are constructed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone