| Facilities brief:
• NIT for the facilities tender held on 22.06.2022.
• Pre- bid Conference held on 12.07.2022 as per schedule.
• Replies to the queries raised by bidders have been prepared. Amended document uploaded along with commercial amendment on 28.09.2022.
• TBO held on 07.10.2022. TC held on 28.11.2022. Price Bid Opened on 16.12.2022 Meeting with L&T held on 18.01.2023. Tender Committee meeting held on 30.01.2023. Bid validity date has been extended 26.06.2023. Tender Cancelled on
01.05.2023. To re-invite the tender after review of specification, scope of work, execution methodology and tender conditions, with revised strategy for tendering.
* Revision of Scope of work, execution methodology etc. under process
* Indent placed. NIT published on 08.08.2023 and PBC held on 29.08.2023 as per schedule. TBO held on 22.01.2024
* Post bid conference held on 19.02.2024 with L&T
* L&T Price bid opened on 26.02.2024. Quoted price 39.05% higher than estimated cost.
* NoA extended to 05.04.2024, overall completion extended from 31.01.2026 to 28.02.2026.
Drilling of wells:
• Drilling to be planned after installation of 4 new well head platforms (WHP). |