Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL & NATURAL GAS CORPORATION LIMITED.
Project Name : DAMAN UPSIDE DEVELOPMENT PROJECT (DUDP) IN TAPTI DAMAN BLOCK.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   54.59

Time Overrun (Months)-    4

Total/Pending/Completed Milestone - 6 / 0 / 6

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
4144.416406.96406.9

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2782.42.34420.53203.26

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20250/02/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2342.780

Ministry Review Date

LatestLastPhysical Progress (%)Status
31-MAY-2580.5Ongoing

Monthly Status

Background Information

Drilling package : ¿ Drilling Rig deployed at all 4 platforms and started drilling at 3 platforms. Location/ Drilling Rig: B -12-24 P/ Discovery-I, B -12-18 P1/ Divine Driller, B-12-18 P2/ FGM, B-12 -2P/ KSN. Drilling under progress in all 4 wells.Facilities brief: • NIT for the facilities tender held on 22.06.2022. • Pre- bid Conference held on 12.07.2022 as per schedule. • Replies to the queries raised by bidders have been prepared. Amended document uploaded along with commercial amendment on 28.09.2022. • TBO held on 07.10.2022. TC held on 28.11.2022. Price Bid Opened on 16.12.2022 Meeting with L&T held on 18.01.2023. Tender Committee meeting held on 30.01.2023. Bid validity date has been extended 26.06.2023. Tender Cancelled on 01.05.2023. To re-invite the tender after review of specification, scope of work, execution methodology and tender conditions, with revised strategy for tendering. * Revision of Scope of work, execution methodology etc. under process * Indent placed. NIT published on 08.08.2023 and PBC held on 29.08.2023 as per schedule. TBO held on 22.01.2024 * Post bid conference held on 19.02.2024 with L&T * L&T Price bid opened on 26.02.2024. Quoted price 39.05% higher than estimated cost. * NoA extended to 05.04.2024, overall completion extended from 31.01.2026 to 28.02.2026. Drilling of wells: • Drilling to be planned after installation of 4 new well head platforms (WHP).

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone