Reported Date :
13-MAR-24
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
4
/
2024
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
10
|
Total/Pending/Completed Milestone -
4
/
0
/
4
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
* Contract awarded to M/s JSC GOLLA ENGINEERING PVT LTD. Chennai. Kick-off meeting held on 25.07.2022.
* Engineering & Procurement, site actvities are in progress. Submitted Process Package on 09.11.2022. Soil sample collection completed at Tatipaka GCS. Bid for TPI (forvthe LSTK project) opened on 21.11.2022 and further work in Progress. Planing Package Approved
* PO placed to M/s OSWAL for GDU and DPD package. PO placed for GEG and Diesel Generator. PO placed for IA Compressor system on 14.09.2023
* 60% model review completed for Mandapeta & Tatipaka GCS.
At Mandapita GCS: Pile work completed. 88 Piles COMPLETED. GEG receieved at JNPT, Navi-Mumbai
* At tatipaka GCS:
¿ Pile work started, further job in progress.
¿ Manufacturing of GDU & DPD is in progress at Vendors works. Stage inspiction by TPI is also being carried out. | |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |