Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : BHARAT PETROLEUM CORPORATION LIMITED.
Project Name : CITY GAS DISTRIBUTION NETWORK PROJECT AT RUPNAGAR.

Reported Date : 26-APR-23

Monthly Report : 4 / 2023

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
172.70172.7

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
122.7600122.76

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20230/06/2023

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
160

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks