M/s Engineers India Limited (EIL) was awarded the NOA on 10.09.2022 to execute the project on an EPC reimbursable basis. M/s Engineers India Limited (EIL) was awarded the NOA on 10.09.2022 to execute the project on an EPC reimbursable basis.TPIA services have been awarded to M/s ICS India, and Material Handling Works to M/s KBUC & Co. Civil works are substantially complete—foundation for all 139 trestles has been completed, with 137 erected and fireproofing completed for 131. RCC paving and drainage in the KOD area are complete, and culvert construction is in progress. Key mechanical erections, including fuel gas KOD, cyclone filters, blowdown drums, and filters, are mostly completed. Fabrication of above-ground piping and 36 pipeline welding is ongoing. The rerouting of the 16 inch HP Kribhco line is in advanced stages, with split tee welding and hydrotesting completed and hot tapping in progress. Composite works by M/s Sopan O&M is in progress, with paving in the Gas Terminal area nearing completion. | • NOA placed on 10.09.2022 to M/s. Engineers India Limited (EIL), Delhi to execute the project on EPC reimbursable basis.
• Engineering under progress. Engineering design basis approved for Process, Instrumentation, Electrical, Structure and Pipelines.
• Procurement under progress for around 43 material requisition (MRs). PO placed for Pressure Vessel, Custody Metering Skid , Cyclone Filters, Gas Metering System, Scrapper Trap & Pig Receiver System and insulating Joints to M/s Advance Electronic System. Mass Flow Meters, Pipelines, gaskets and fittings has been received
on site.
• Barricading and Enabling Works has been awarded to M/s Voltonix Infratech Ahmedabad on 07.02.2023: Work completed.
• Deconstruction and Piling Works has been awarded to M/s North East Engineering & construction Guwhati on 13.02.2023. Work completed.
• TPIA Works has been awarded to M/s ICS India Pvt Ltd Pune on 28.02.2023.
* Work for Civil and Infrastructure has been awarded on 21-09-23 to M/s Ray Engineering Pvt. Ltd. Mumbai. Fabrication of flare pipeline trestles is under progress.
• Material Handling Works Tender is awarded to M/s KBUC & Company on 23.05.2023
* Composite works Contractor, M/s Sopan O&M Company, Ahmedabad: Awarded on 12.10.2023. Excavation and foundation raft of CBD sump has been completed, further walls for CBD is under progress. CRWS pit is under construction along with other civil works which includes foundations for vessels and platform etc. Fabrication of piping is under progress at fabrication yard and Erection on site has been also started and is under progress |