Work progress is 98.3%. Foundation work for all 139 nos. trestles has been completed. Fabrication of 139
trestles structures has been completed and 137 nos. are erected, Fire proofing work completed for 127 nos. of
trestles and is under progress. Further erection of trestles/platforms is under progress. Erection of cable tray and
its structure is also under progress. All civil work (RCC Paving, drainage work etc.) has been completed in KOD
area.
¿
¿ Erection Erection of 36 pipeline work (12932/26800 IM) is under progress using automatic welding machine.
Rerouting work for 16 HP Kribhco Line has been started. Hot Tapping Team completed welding of split tee at
one end. Erection of rerouted portion of pipeline is nearing completion. | • NOA placed on 10.09.2022 to M/s. Engineers India Limited (EIL), Delhi to execute the project on EPC reimbursable basis.
• Engineering under progress. Engineering design basis approved for Process, Instrumentation, Electrical, Structure and Pipelines.
• Procurement under progress for around 43 material requisition (MRs). PO placed for Pressure Vessel, Custody Metering Skid , Cyclone Filters, Gas Metering System, Scrapper Trap & Pig Receiver System and insulating Joints to M/s Advance Electronic System. Mass Flow Meters, Pipelines, gaskets and fittings has been received
on site.
• Barricading and Enabling Works has been awarded to M/s Voltonix Infratech Ahmedabad on 07.02.2023: Work completed.
• Deconstruction and Piling Works has been awarded to M/s North East Engineering & construction Guwhati on 13.02.2023. Work completed.
• TPIA Works has been awarded to M/s ICS India Pvt Ltd Pune on 28.02.2023.
* Work for Civil and Infrastructure has been awarded on 21-09-23 to M/s Ray Engineering Pvt. Ltd. Mumbai. Fabrication of flare pipeline trestles is under progress.
• Material Handling Works Tender is awarded to M/s KBUC & Company on 23.05.2023
* Composite works Contractor, M/s Sopan O&M Company, Ahmedabad: Awarded on 12.10.2023. Excavation and foundation raft of CBD sump has been completed, further walls for CBD is under progress. CRWS pit is under construction along with other civil works which includes foundations for vessels and platform etc. Fabrication of piping is under progress at fabrication yard and Erection on site has been also started and is under progress |