Pipeline laying cumulative progress is 117.5 kms, work in progress
HDD works, civil construction work at all stations is under progress
ROU issues in Purba Mednipur, Bankura and Purba Bardhamann apprised to district administration for support and earliest resolution | Pipeline laying works PO placed on 12.03.2024
Line pipe total delivery to project site is completed
OFC manufacturing is completed, delivery in progress
6(1) notification of all 5 districts of HPPL published in extraordinary gazette of India as per P&MP act 1962
CA HPPL has passed ROU awards for 15 villages in Hooghly district and 7 villages in Paschim Medinipur district.
Factories approval obtained for Haldia Dispatch station and Panagarh Receipt station
CCOE construction approval obtained for pipeline and Pumping station |