Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : HINDUSTAN PETROLEUM CORPORATION LIMITED.
Project Name : HALDIA PANAGARH PIPELINE PROJECT.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 21 / 6 / 15

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
101001010

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
509.1917.3620.05546.6

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/20250/011/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
323323

Ministry Review Date

LatestLastPhysical Progress (%)Status
79.09Ongoing

Monthly Status

Background Information

Pipeline laying cumulative progress is 91.9 kms, work in progress HDD works, civil construction work at all stations is under progress ROU issues in Purba Mednipur, Bankura and Purba Bardhamann apprised to district administration for support and earliest resolutionPipeline laying works PO placed on 12.03.2024 Line pipe total delivery to project site is completed OFC manufacturing is completed, delivery in progress 6(1) notification of all 5 districts of HPPL published in extraordinary gazette of India as per P&MP act 1962 CA HPPL has passed ROU awards for 15 villages in Hooghly district and 7 villages in Paschim Medinipur district. Factories approval obtained for Haldia Dispatch station and Panagarh Receipt station CCOE construction approval obtained for pipeline and Pumping station

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone