Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : LAYING OF NATURAL GAS PIPELINE FROM HAZARIBAGH TO RANCHI.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
202.070202.07

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
48.244.7052.94

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20260/02/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
48.590

Ministry Review Date

LatestLastPhysical Progress (%)Status
42.95Ongoing

Monthly Status

Background Information

1. Statutory Approvals : Overall Progress (Clearances & Permissions): 58.35% completed 2. Ordering : Overall Progress of work order(s): 100% completed Overall Progress of purchase order(s): 94.68% completed 3. Manufacturing & Delivery Status : Overall Progress: 66.16% completed 4. Engineering : Design & Engineering: 86.13% Completed 5. Construction : Overall Progress: 0.82% completed1. Statutory Approvals : Overall Progress: 11.7% completed 2. Ordering : Overall Progress of work order(s): 29.46% completed Overall Progress of purchase order(s): 70.61% completed 3. Manufacturing & Delivery Status : Overall Progress: 3.65% completed

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks