Pipeline Laying Progress: Sch./Act 100%/81.75%.
Major construction activity: ROU handed over for a total 118.82 km of length ( 59 segments). Welding: 111.23
KM, trenching: 110.42 KM, lowering 110.10 Km & Back filling: 109.03 Km Complete ROU for 55 nos. segment
has been handed over. laying of underground lines for 52 nos. segment completed.
¿
Terminal works: Sch vs Act-100%/71.92%
Terminal Work at NK-IV, NK-I, NK-CTF, SS-CTF , Sob-I, Sob-II, Jotana GGS, Sob-CTF, Lanwa-I & Lanwa-70 is
in progress.
¿
¿ E&I work of terminal at NK-I, NK-IV, NK-CTF & Jotana in progress
Hydro/Pre-commissioning: Sch/Act 100%/42.05%.
¿ Hydro testing of 51 nos. underground pipeline out of 65 completed.
Commissioning : Sch/Act 99.12%/20.28%
¿ 47 nos. segments commissioned out of 65 nos | * Contract awarded to M/s potaliya Enterprises.
* Pre-Engineering survey, Engineering and procurement started.
* Insurance & Planning Package approved.
* Site visit completed on 11.11.2022. Contour & Topographical survey completed. Geo-technical survey in progress.
* ROU handed over for a total 56.25 km of length at Becharaji GGS-I&II area, Sob, Balol, Linch and santhal area.
* Grading: 56.25 Km, Welding: 56 Km, tranching: 52.93 Km, lowering 52.44 Km and Back filling: 50.77 Km done.
* Further work in progress |