Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL & NATURAL GAS CORPORATION LIMITED.
Project Name : OLD PIPE LINE REPLACEMENT (OPRP) GROUP-A.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 5 / 0 / 5

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
173.030169.84

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
137.992.41.05140.45

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20250/07/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
400

Ministry Review Date

LatestLastPhysical Progress (%)Status
31-MAY-2584Ongoing

Monthly Status

Background Information

Pipeline Laying Progress: Sch./Act 100%/81.75%. Major construction activity: ROU handed over for a total 118.82 km of length ( 59 segments). Welding: 111.23 KM, trenching: 110.42 KM, lowering 110.10 Km & Back filling: 109.03 Km Complete ROU for 55 nos. segment has been handed over. laying of underground lines for 52 nos. segment completed. ¿ Terminal works: Sch vs Act-100%/71.92% Terminal Work at NK-IV, NK-I, NK-CTF, SS-CTF , Sob-I, Sob-II, Jotana GGS, Sob-CTF, Lanwa-I & Lanwa-70 is in progress. ¿ ¿ E&I work of terminal at NK-I, NK-IV, NK-CTF & Jotana in progress Hydro/Pre-commissioning: Sch/Act 100%/42.05%. ¿ Hydro testing of 51 nos. underground pipeline out of 65 completed. Commissioning : Sch/Act 99.12%/20.28% ¿ 47 nos. segments commissioned out of 65 nos* Contract awarded to M/s potaliya Enterprises. * Pre-Engineering survey, Engineering and procurement started. * Insurance & Planning Package approved. * Site visit completed on 11.11.2022. Contour & Topographical survey completed. Geo-technical survey in progress. * ROU handed over for a total 56.25 km of length at Becharaji GGS-I&II area, Sob, Balol, Linch and santhal area. * Grading: 56.25 Km, Welding: 56 Km, tranching: 52.93 Km, lowering 52.44 Km and Back filling: 50.77 Km done. * Further work in progress