Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : HINDUSTAN PETROLEUM CORPORATION LIMITED.
Project Name : CONSTRUCTION OF LPG FACILITIES AT KAMARDANGA, ASSAM.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
156.36156.36156.36

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
36.522.42.141.02

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20277/20277/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
28.828.8

Ministry Review Date

LatestLastPhysical Progress (%)Status
31.5Ongoing

Monthly Status

Background Information

• Soil Investigation completed. • Topography survey completed. • Work in progress for boundary wall works and land filling works. • BQ plate identification completed. • Construction of vibro-stone columns for MSV ground improvment completed. Load testing completed. • Moorum blanketing work completed. • PCC for MSV completed. Reinforcement laying works in progress. • 50% Raft RCC casting completed. • Plate rolling completed. LS welding of shell in progress • Water Tank: Sand filling, WSEL layers and Anti-corrosive BT layer laying completed. • Fabrication for shells in progress. • • Wagon Gantry Works: Excavation and casting of footing started. 35 Footing completed. • Shell fabrication works in progress. • • Buildings Works: Roof slabs casted for Driver amenity building, VCB Room, MCC Room, Security Cabin, Weigh Bridge Cabin and Admin building (both ground floor and 1st floor). • Brick work and plastering in progress at driver’s rest, Security cabin room, ware house and admin building. • Column casting completed for Fire engine shed and TT Gantry. Column casting in progress for LPG Pump House. Construction will start after land procurement. Soil Investigation completed. Topography survey completed. Payment for land done by HPCL. Possession certificate received. Land handover yet to be received. PO Placed for Engineering Consultancy, Security services ,BQ plates, MSV works, TPI services and boundary wall construction. TE completed for Land filling, MS plates. Tender floated for building works, water tank construction, LPG Pump and compressor

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone

&